How to become a property developer in Dubai (2026): licence, escrow and joint ventures
To develop and sell off plan in Dubai, a company needs a Dubai Land Department real estate development licence at AED 25,000 a year, a place on the Register of Real Estate Developers, a registered project at AED 150,000 and a project escrow account with an approved trustee bank. This guide sets out the order of those steps, how escrow money is released, what happens at completion, and how a landowner can take part through a development agreement, a joint venture company or Musataha.

This article discusses regulation and costs that can change. Confirm current requirements with the relevant authority before acting.
To become a property developer in Dubai, a company needs a real estate development licence from the Dubai Land Department, which costs AED 25,000 a year and requires the land to be owned by the licence holder or one of its partners, according to the Department's service page accessed on 7 November 2026. Before it sells a single unit off plan it must also register the project, at AED 150,000, and open a project escrow account with an approved trustee bank under Law No. 8 of 2007.
This guide is for a family office or private investor who owns a plot, or will buy one, and wants to develop and sell off plan or bring the land into a venture with a developer. Choosing and checking the land is covered in our guide to buying a development plot in Dubai and Abu Dhabi. This one covers the order of approvals, how escrow money moves, cancellations, handover and landowner structures.
How to become a property developer in Dubai: licence and DLD developer registration
The steps run in a fixed order, each depending on the one before.
- Trade licence. The Land Department's licence page says the application is submitted through the Dubai Department of Economy and Tourism. A free zone company needs a no objection certificate from its own licensing authority.
- Development activity licence. The Land Department lists the real estate development activity at AED 25,000 a year, plus AED 20 in knowledge and innovation charges. Ownership of the land is verified electronically, and the page states that ownership "must be under the license holder or one of the partners."
- Trakheesi registration. The same page says the developer registers in the Trakheesi system on the Land Department's website and needs a Trakheesi permit to market a project.
- Developer register. Article 4 of Law No. 8 of 2007, issued on 6 May 2007, says the Land Department keeps a Register of Real Estate Developers and that no developer may do business unless it is listed there and licensed by the competent entities.
- Final building permits from the planning authority for the area, then project registration, escrow, advertising permission and sales, then construction, completion and handover, each covered below.
The ownership rule in step 2 shapes the structure from day one. Either the landowner company takes the development licence, or the landowner becomes a partner in the licensed developer. A third route, where the landowner stays outside and signs a development agreement, is recognised at project registration and discussed below. Article 16 of the law makes development without a licence an offence punishable by imprisonment, a fine of at least AED 100,000, or both.
What does off plan project registration in Dubai require?
The Land Department's register project service is the gate between a permitted building and an off plan launch. It runs through the Oqood portal: the developer submits the request and documents, opens a unit survey request and a technical report request, asks the account custodian, meaning the trustee bank, to open the escrow account, and then pays the fee once the Department has audited the file. The output is an electronic Real Estate Project Approval Certificate.
The conditions on the page are specific.
- The land must be in a freehold or long term lease area.
- A title deed must exist. The page says "preliminary sales certificates are not accepted", so a plot still being paid for in instalments cannot carry a project.
- The developer must be registered in Trakheesi, and units must be uploaded to the Survey Department with approved plans from a Dubai planning authority.
- A 30 per cent guarantee must be given, by completing 30 per cent of construction, by a bank guarantee covering 30 per cent of construction, or by a cash deposit equal to 30 per cent.
The documents include a consultant letter, a district cooling agreement, an investor compensation mechanism, final building permits, a master developer NOC approving the project name, off plan sale and marketing, a bank guarantee, and, where the landowner differs from the developer, a development agreement with a fee of 4 per cent of land value.
The fee is AED 150,000, plus knowledge and innovation fees of AED 10 each. The Department's FAQs say the bank guarantee is released at 100 per cent completion according to the technical report, so treat it as credit committed for the whole build.
How does a developer's escrow account work in Dubai?
Law No. 8 of 2007 sets the frame. Article 6 says a developer that wants to sell off plan must apply for an escrow account, supported among other things by the title deed, approved designs, a certified statement of costs and revenues and a standard sale contract. Article 9 says each account is in the project's name, is "dedicated exclusively to the construction" of that project, cannot be attached by the developer's creditors, and that each project needs its own account. Article 13 says that if a developer borrows against the project, the lender pays the loan into the escrow account.
The trustee is a bank. The Land Department's FAQs say it must be licensed by the Central Bank of the UAE to take third party deposits, operate in Dubai and be approved by RERA. The Department announced in December 2024 that the International Development Bank's UAE branch had joined the authorised list, without stating how many banks are on it, so ask for the current list before choosing one.
Money comes out against construction, not against sales. The FAQs say the written agreement with the trustee lists the major construction milestones; the developer notifies the trustee when one is complete, the trustee's engineer inspects the site, and payment is released only after verification. Permitted payments are mainly to contractors, consultants and marketing, and marketing is capped at 5 per cent of total sales.
Before any release, the disbursement mechanism has to be activated. The Department's activation service, which is free and takes three business days, requires the developer to meet the project's financial risk standards and to hold a Department technical report no older than three months. It sets four routes: a bank guarantee, which activates the account for construction up to 20 per cent completion; the developer's own contribution; bank financing deposited by the mortgaging bank; or financial solvency, which activates releases as a percentage of construction after 20 per cent completion. The page does not state that percentage. The FAQs add that a fresh technical report fee is due whenever the last report is more than three months old.
When can a developer advertise and sell, and what is Oqood?
Article 5 of Law No. 8 of 2007 bars a developer from advertising off plan sales in local or international media, or exhibiting for that purpose, without the Department's prior written authorisation. The Department's FAQs say a new project may be launched or announced only after all registration steps are complete and the accreditation certificate is issued.
Each campaign then needs a permit through Trakheesi. The Department's advertising permit page lists AED 5,000 for a project launch event permit and AED 1,000 for other permits, plus AED 20 in knowledge and innovation fees. At exhibitions only preliminary reservations are allowed, and a Dubai off plan project must be registered with the Escrow Account Department to be shown.
Every sale must then be registered. Article 3 of Law No. 13 of 2008, issued on 14 August 2008, says an off plan sale is void unless entered in the Interim Property Register, and Article 10 voids any sale contract signed before the project is approved. The Department's initial sale service runs through Oqood, charges 2 per cent of the sale value to each party plus a developer self registration fee of AED 1,000, and says the contract must be registered within 90 days of signing. How the 4 per cent is split between developer and buyer is set in the sale contract.
The clock starts at the sales permission. Article 17 of Law No. 8 of 2007 lets the Department strike a developer off the register if it fails, without good reason, to start construction within six months of receiving permission to sell off plan. Appoint the contractor before launch.
What happens if a buyer cancels or the project stalls?
Article 11 of Law No. 13 of 2008 gives the developer a route when a buyer defaults: the developer notifies the Department, which serves the buyer a 30 day notice to perform. The original text let the developer keep up to 30 per cent of payments. Law No. 19 of 2017 replaced that with bands tied to completion, which our payment plans guide sets out.
Law No. 19 of 2020 changed it again. Al Tamimi and Company reported in March 2021 that it was passed on 24 November 2020 and published on 13 December 2020, that a developer "must return all amounts received from a purchaser" if works had not commenced at termination, and that completion is now measured on the project as a whole rather than the buyer's unit. Khaleej Times reported on 15 December 2020 that the refund applies where construction never started for reasons beyond the developer's control or where RERA cancelled the project. The two summaries differ, and we could not retrieve the official text, so confirm the wording with counsel.
When a project is cancelled, the Department's FAQs say the account passes to its liquidation section, which asks the developer to refund investors within 60 days of the decision, a period RERA may extend. Disputes over cancelled and unfinished projects go to a special tribunal set up in December 2020, which Khaleej Times called Decree No. 33 of 2020 and Al Tamimi called Law No. 33 of 2020.
Under Article 15 of Law No. 8 of 2007, if a project is left incomplete in an emergency, the escrow agent must either complete it or refund depositors. Sales money cannot rescue a project in trouble, because it is ring fenced for construction; equity and the guarantee carry the risk.
How do completion, handover and the 5 per cent retention work?
Completion is certified by the planning authority. Dubai Municipality's procedure for multistorey buildings, version 4 dated 10 May 2020, requires structural inspections during the build and, once the work is reported finished, a final inspection by a joint team including Building Control, Survey, Dubai Civil Defence and the RTA, after which the completion certificate is issued and services connected.
Title follows completion. Article 8 of Law No. 13 of 2008 requires the developer to register the completed project in the Property Register once it receives the completion certificate, and units pass into buyers' names once each buyer has met all contractual obligations. The Department's FAQs say the developer appoints an approved survey company and asks for the project to be moved to 100 per cent completed status. Article 12 says the registered area is deemed correct: the developer cannot charge for an increase after delivery, but must compensate a buyer for a decrease that is not inconsequential.
The retention comes last. Article 14 of Law No. 8 of 2007 requires the escrow agent to keep 5 per cent of the account's total value once the completion certificate is issued and to release it one year after units are registered in buyers' names. The Department's FAQs describe it as cover for defects visible at completion or appearing within a year of handover, and word the period as one year after project completion. Where the two differ, the law governs, so model the retention as released a year after title deeds are issued, not a year after the completion certificate.
How does a joint venture with a landowner work in Dubai, and where does Musataha fit?
A landowner who does not want to be the developer has three recognised routes, and each protects the parties differently.
- Development agreement. The landowner keeps title and contracts with a licensed developer, who registers the project. The Land Department's project registration service requires the agreement and a fee of 4 per cent of land value. Hadef and Partners, writing on 14 March 2025, list the terms that protect a landowner: approval rights over critical decisions, a defined profit share, milestones with remedies if they are missed, and an agreed minimum sale price. For the developer they list a defined scope, a fee structure and authority on key matters.
- Joint venture company. The landowner and developer become shareholders in one company, and the shareholders' agreement is the main deal document. STA Law Firm noted in May 2020 that UAE company law does not recognise a joint venture entity as such, so the parties use an existing form such as a limited liability company or a free zone company. This route fits the licence rule directly, because the land is owned by the licence holder or one of its partners.
- Musataha. The owner grants a right to build on and use the land for a term. Executive Council Resolution No. 30 of 2013, issued on 18 September 2013, sets Dubai's registration fee at 1 per cent of the consideration. Under the new UAE Civil Transactions Law, Federal Decree Law No. 25 of 2025, in force since 1 June 2026, Al Tamimi and Company reported on 7 July 2026 that Article 1255 requires a Musataha to be created by a registered contract and that an unregistered one is deemed void. Clyde and Co reported in June 2026 that the former 50 year statutory cap has been removed. Older commentary, including STA Law Firm's in 2020, still cites the 50 year limit, so check which code governs any existing agreement.
Usufruct is the lighter alternative: Article 4 of Law No. 7 of 2006 allows usufruct or leasehold of up to 99 years for non UAE nationals in designated areas, and Resolution No. 30 of 2013 sets its registration fee at 2 per cent of the property value.
Registration is the protection that matters most in every route. Article 9 of Law No. 7 of 2006 says a transaction creating or transferring a real property right is not valid unless recorded in the register. STA Law Firm cited a Dubai appeal, No. 250 of 2017, in which a builder under an unregistered agreement lost the building to the landowner. Beyond that, the landowner's exposure is the developer's balance sheet, which the 30 per cent guarantee and a step in right partly cover; the developer's is its authority to sell, which the registered agreement must state.
What is different in Abu Dhabi?
Abu Dhabi regulates developers under Law No. 3 of 2015, which CMS reported was published on 30 June 2015 and took effect on 1 January 2016. Its summary describes a developer register, separate approval to market, registration of every off plan sale on the Interim Real Estate Register, an escrow account for each project or phase, no release until the project is at least 20 per cent complete, and a retention of at least 5 per cent for at least a year after completion.
The law was amended by Law No. 2 of 2025. King and Spalding reported on 12 May 2026 that Article 19 bars escrow funds from paying the land price or broker commissions, and that Decision No. 24 of 2025 lets the Abu Dhabi Real Estate Centre approve releases before 20 per cent completion for a developer registered in Abu Dhabi for at least four years, with at least three projects delivered on or before schedule, no violations in the previous 12 months, and a first demand bank guarantee of at least 20 per cent of construction cost. The Abu Dhabi Media Office announced on 27 March 2026 that the Department of Municipalities and Transport had issued Decisions No. 24, 25, 26 and 165 of 2025, the last setting what a developer keeps when a buyer breaches an off plan contract and the refund timetable once a cancelled unit is resold. The release does not publish the percentages.
What it means for investors
Becoming a developer in Dubai is less a licence than a capital plan. The fixed fees, AED 25,000 a year and AED 150,000 per project on the Department's figures accessed on 7 November 2026, are modest against a building. What shapes returns is the 30 per cent guarantee, land funded outside escrow, the six month construction start, and the 5 per cent retained until a year after title deeds issue. Model those four items alongside sales to see the true equity requirement and peak exposure.
For a landowner, choosing between a sale, a development agreement, a joint venture company and a registered Musataha is a choice about control and the timing of cash. A sale gives certainty now; the other routes share profit and delivery risk, and the 4 per cent of land value charged at project registration belongs in that comparison.
For a buyer in the United States, Canada or Latin America, the dirham is pegged at AED 3.6725 to the US dollar, so a dollar funded construction budget carries no currency risk against the dollar. A US citizen or resident who is an officer, director or shareholder of a foreign company may have to file IRS Form 5471, according to an IRS page reviewed on 19 April 2026; confirm your position with a US tax adviser, and see our US investors page. Canadian and Latin American investors should check the equivalent rules with an adviser at home.
What we recommend
Sequence the project before you buy or commit the land. Confirm that the land sits in a freehold or long term lease area, that the title deed is issued rather than a preliminary certificate, and which company will hold the development licence. Then build the budget around the guarantee, the escrow activation route and the retention, not only the construction cost. Confirm the current position with the authority before relying on it, because fees, guarantee routes and release conditions change by resolution.
If you own land and prefer not to develop it yourself, agree the structure first: a registered development agreement, a joint venture company, or a Musataha registered under the new Civil Transactions Law. Castilion Estates presents plots, joint venture opportunities and whole assets under NCNDA through its commercial desk. For logistics land, our build your own warehouse service covers the plot search, the consultant and contractor team, and the programme to the completion certificate. Structure legal and tax matters with your own counsel.
Questions and answers
How much does it cost to become a property developer in Dubai?
What is a RERA trustee account?
What is a development agreement in Dubai and when is it needed?
Can a developer use escrow money to buy the land?
When is the 5 per cent escrow retention released in Dubai?
Is Musataha an alternative to selling land to a developer?
Sources
- Real estate licence service, real estate development activity, land ownership by the licence holder or a partner, AED 25,000 annual fee, application through the Department of Economy and Tourism, Trakheesi permit to market (opens in a new tab). Dubai Land Department. Accessed .
- Register project service, Oqood submission, escrow account opened by the account custodian, final building permits, master developer NOC, 30 per cent guarantee, AED 150,000 fee, development agreement and 4 per cent of land value (opens in a new tab). Dubai Land Department. Accessed .
- Request to activate an escrow account, disbursement mechanism, technical report not older than three months, bank guarantee route to 20 per cent completion, free service, three business days (opens in a new tab). Dubai Land Department. Accessed .
- Development services FAQs, trustee licensed by the Central Bank and approved by RERA, milestone releases verified by the trustee's engineer, marketing capped at 5 per cent of sales, AED 15,000 technical audit, 60 day refund on cancelled projects (opens in a new tab). Dubai Land Department. Accessed .
- Real estate advertising permit service, project launch event permit AED 5,000, other permits AED 1,000, off plan projects at exhibitions must be registered with the Escrow Account Department (opens in a new tab). Dubai Land Department. Accessed .
- Initial sale registration through Oqood, 2 per cent from each party, developer self registration fee of AED 1,000, registration within 90 days of signing (opens in a new tab). Dubai Land Department. Accessed .
- International Development Bank joins the banks authorised as escrow account trustees, a separate account for each project, December 2024 (opens in a new tab). Dubai Land Department. Accessed .
- Law No. 8 of 2007 concerning escrow accounts for real estate development in Dubai, Articles 4 to 17, issued 6 May 2007 (opens in a new tab). Dubai Legislation Portal. Accessed .
- Law No. 13 of 2008 regulating the interim property register in Dubai, Articles 3, 4, 8, 10 and 12, issued 14 August 2008 (opens in a new tab). Dubai Legislation Portal. Accessed .
- Law No. 7 of 2006 concerning real property registration in Dubai, Article 4 on usufruct and leasehold of up to 99 years, Article 9 on recording rights in the register (opens in a new tab). Dubai Legislation Portal. Accessed .
- Executive Council Resolution No. 30 of 2013 on Land Department fees, Musataha 1 per cent of the consideration, usufruct 2 per cent of the property value, long lease 4 per cent, issued 18 September 2013 (opens in a new tab). Dubai Legislation Portal. Accessed .
- Procedure of issuing building permit and building completion certificate, multistorey buildings, version 4, 10 May 2020, final inspection by a joint team before the completion certificate (opens in a new tab). Dubai Municipality. Accessed .
- Department of Municipalities and Transport issues Decisions No. 24, 25, 26 and 165 of 2025 under Law No. 3 of 2015 as amended by Law No. 2 of 2025, 27 March 2026 (opens in a new tab). Abu Dhabi Media Office. Accessed .
- Dubai amends interim registration law, Law No. 19 of 2020 passed 24 November 2020 and published 13 December 2020, full refund where works have not commenced, completion measured on the whole project, March 2021 (opens in a new tab). Al Tamimi and Company. Accessed .
- Sheikh Mohammed issues new Dubai law on unfinished and cancelled real estate projects, Law No. 19 of 2020 and the special tribunal, 15 December 2020 (opens in a new tab). Khaleej Times. Accessed .
- Musataha rights under the UAE Civil Transactions Law 2025, Article 1255 registration requirement, in force 1 June 2026, 7 July 2026 (opens in a new tab). Al Tamimi and Company. Accessed .
- New UAE Civil Code, what real estate stakeholders need to know, Federal Decree Law No. 25 of 2025, removal of the 50 year Musataha cap, June 2026 (opens in a new tab). Clyde and Co. Accessed .
- Real estate joint development arrangements in Dubai and the UAE, company route, joint development agreement and Musataha, risks of unregistered agreements, 12 May 2020 (opens in a new tab). STA Law Firm via Mondaq. Accessed .
- Overview of development management agreements in the UAE, landowner and developer protections, 14 March 2025 (opens in a new tab). Hadef and Partners. Accessed .
- Abu Dhabi off plan 2.0, escrow, guarantees and governance, Law No. 3 of 2015 as amended by Law No. 2 of 2025, Article 19 and Decision No. 24 of 2025, 12 May 2026 (opens in a new tab). King and Spalding. Accessed .
- New Abu Dhabi real estate law, Law No. 3 of 2015 published 30 June 2015 and effective 1 January 2016, developer register, escrow, 20 per cent threshold, 5 per cent retention (opens in a new tab). CMS. Accessed .
- Certain taxpayers related to foreign corporations must file Form 5471, page reviewed 19 April 2026 (opens in a new tab). Internal Revenue Service. Accessed .
Where Castilion can help
- Investment advisoryEvidence based advice for long term holders.
- Asset protection and structuringHow to hold property in the UAE.
Weighing a decision this touches?
Our licensed team can talk it through with you, in confidence and without obligation.
Talk to an Advisor