Dubai Metro Blue Line is 29% built as the 9 September 2029 opening holds
The Dubai Metro Blue Line has reached 29% overall completion, with tunnel excavation at 55% and underground stations at 32%, the Government of Dubai Media Office said on 22 November 2026 as Sheikh Hamdan bin Mohammed reviewed the project and a new train design. For buyers the release confirms the 30 kilometre route, its 14 stations and the seven districts it serves, and The National reported the same day that the AED 20.5 billion line is scheduled to open on 9 September 2029.

The Dubai Metro Blue Line has reached 29% overall completion, with 55% of tunnel excavation and 32% of underground station works done, the Government of Dubai Media Office said on 22 November 2026 as Sheikh Hamdan bin Mohammed bin Rashid Al Maktoum, Crown Prince of Dubai, reviewed progress and a new train design. The National reported the same day that the AED 20.5 billion line is scheduled to open on 9 September 2029. For a buyer the release is a confirmed alignment: 30 kilometres, 14 stations and seven named districts, several of which have had no metro access until now.
What Dubai reported on 22 November 2026
The release gives the progress by component. Overall completion is 29%. Tunnel excavation is 55% complete, underground stations 32%, bridge piers 62%, bridge works 17% and above ground stations 16%. More than 14,000 workers have put in over 33 million working hours, the release said. Khaleej Times and Gulf News carried the same figures on 22 November 2026.
The National added the budget and the date. The project costs AED 20.5 billion and is scheduled to open on 9 September 2029, the 20th anniversary of the Dubai Metro's launch. The network will then stretch to 131 kilometres with 78 stations served by 168 trains, The National reported. Sheikh Hamdan said, as quoted by The National: "Work is gathering pace ahead of the scheduled opening on 9 September 2029."
Where the 14 stations go
The route runs 30 kilometres, of which 15.5 are underground and 14.5 above ground, according to the release. It has 14 stations, including a station at Dubai Creek Harbour and three interchanges: two connecting the line to the Red and Green Lines and one linking the Blue Line's two branches. The districts named are Mirdif, Al Warqa'a, International City, Dubai Silicon Oasis, Dubai Academic City, Dubai Festival City and Dubai Creek Harbour.
The release also describes the line's first crossing of Dubai Creek, a 1.3 kilometre bridge built from precast concrete segments. The National reported that tunnelling was inaugurated in May 2026.
What the new trains carry
The train design reviewed on 22 November 2026 has a design capacity of 675 passengers per journey and a total capacity of 1,246, the release said. The interior is split into Gold Class, Silver Class and a dedicated carriage for women and children. Cameras on the trains detect obstacles on the track, count passengers and monitor occupancy. Gulf News reported the same capacities on 22 November 2026, describing the 1,246 figure as the maximum.
The inspection and research initiatives
The Roads and Transport Authority's Rail Agency has developed an Automated Rail Infrastructure Inspection System, called ARIIS, which uses LiDAR and artificial intelligence and targets an 80% reduction in inspection time and 90% early fault detection, the release said. The RTA is also building a research and development centre with CASCO Signal, which Khaleej Times described on 22 November 2026 as housing the Middle East's first train systems development laboratory. The nol card moves to a new nol Jaywan card this month with Al Etihad Payments, a subsidiary of the Central Bank of the UAE, the release said.
The Blue Line is one of three rail announcements this month. The Executive Council approved an AED 2 billion Metro extension to Al Maktoum Airport City on 10 November 2026, and the RTA and Skyports certified the Dubai Marina vertiport on 18 November 2026.
What it means for investors
First, the release names districts, not prices. Nothing in it or in the coverage attaches a value to a home near a Blue Line station, and we do not estimate one. The useful reading is about access. International City, Dubai Silicon Oasis and Dubai Academic City are large rental districts that have relied on buses and cars, and the release confirms they get stations on a 30 kilometre line due in September 2029. A landlord in those districts should check the distance from a building to the nearest planned station before buying.
Second, the stock Castilion Estates lists near the route. In Al Jaddaf, which faces Dubai Festival City across the Creek and is served today by the Green Line's Creek and Al Jadaf stations, Binghatti is building Binghatti Ghost, a residential building of 770 homes, and Binghatti Ivory, a 25 storey tower of 332 homes, both with studios to two or three bedroom apartments. In Dubai Land Residence Complex, about five minutes from Dubai Academic City by the developer's account, The Archive by Imtiaz is listed from AED 666,000 on a 50/50 or 60/40 post handover plan, with handover scheduled for the third quarter of 2028, verified on 3 November 2026.
Third, the dated market frame. Khaleej Times reported on 9 November 2026, from Dubai Land Department data analysed by Property Finder, that Dubai recorded 11,883 transactions worth AED 34.8 billion in October 2026, of which 5,304 were resales and 6,579 were primary deals, with 3,811 mortgages registered in the month worth AED 7.32 billion. The same report noted that the Central Bank of the UAE raised its base rate from 3.65% to 3.9% on 16 September 2026.
Fourth, for a buyer in the United States, Canada or Latin America. The dirham is pegged at AED 3.6725 to the US dollar, so an AED 666,000 apartment is about USD 181,000 with no currency risk against the dollar. Freddie Mac put the US 30 year fixed rate at 7.28% on 19 November 2026, up from 7.11% the week before. Owners who report foreign property at home should confirm the rules with an adviser; our US investors page lists the questions.
Fifth, financing. The Central Bank of the UAE caps an expatriate's loan at 80% of value on a first home below AED 5 million, 60% on an investment property and 50% on any off plan purchase, with a maximum term of 25 years, under Article 3 of its Regulations Regarding Mortgage Loans. A non resident buying off plan near the Blue Line therefore funds the construction instalments from cash and arranges a loan at or near handover on a bank's own non resident terms. Our guide to how off plan purchases work sets out the sequence.
What to watch
Three figures will show whether the line holds its schedule: the next completion percentage the RTA publishes against the 29% of 22 November 2026, the completion of the 1.3 kilometre Creek bridge, and the delivery of the first new trains for testing. Castilion Estates presents three projects in districts the Blue Line will serve and will report each milestone.
Questions and answers
When will the Dubai Metro Blue Line open?
Which areas of Dubai will the Blue Line serve?
Does a metro line raise property prices near its stations?
Can a buyer from the United States or Canada finance an apartment near the Blue Line?
Sources
- Government of Dubai Media Office release on Hamdan bin Mohammed reviewing Blue Line progress, 29% overall completion and the component percentages, more than 14,000 workers and 33 million working hours, the 30 kilometre route and 14 stations, the seven districts, the new train with 675 design and 1,246 total capacity, the ARIIS inspection system, the CASCO Signal research centre, the Train Systems Simulator, the 1.3 kilometre Creek bridge and the nol Jaywan cards, 22 November 2026 (opens in a new tab). Government of Dubai Media Office. Accessed .
- The National on the AED 20.5 billion cost, nearly 30% completion, the 9 September 2029 opening on the Metro's 20th anniversary, the network reaching 131 kilometres, 78 stations and 168 trains, the Gold Line of AED 34 billion and 42 kilometres due on 9 September 2032, and the Hamdan bin Mohammed quotation, 22 November 2026 (opens in a new tab). The National. Accessed .
- Khaleej Times on the nearly 30% completion figure, the 14,000 workers and 33 million working hours, the 9 September 2029 opening and the research and development centre with CASCO Signal, 22 November 2026 (opens in a new tab). Khaleej Times. Accessed .
- Gulf News on the 29% completion, the 675 passenger design capacity and 1,246 maximum capacity of the new trains, and the Gold Class, Silver Class and women and children carriage, 22 November 2026 (opens in a new tab). Gulf News. Accessed .
- Khaleej Times on Property Finder's analysis of Dubai Land Department data for October 2026, 11,883 transactions worth AED 34.8 billion, 3,811 mortgages worth AED 7.32 billion, 5,304 resales and 6,579 primary deals, and the Central Bank base rate rise to 3.9% on 16 September 2026, 9 November 2026 (opens in a new tab). Khaleej Times. Accessed .
- Central Bank of the UAE Regulations Regarding Mortgage Loans, Circular 31/2013, Article 3, loan to value limits of 80% for an expatriate's first home below AED 5 million, 60% on an investment property and 50% off plan, maximum term 25 years (opens in a new tab). Central Bank of the UAE Rulebook. Accessed .
- Freddie Mac Primary Mortgage Market Survey, US 30 year fixed rate of 7.28% and 15 year rate of 6.66% as of 19 November 2026, up from 7.11% and 6.45% the week before (opens in a new tab). Freddie Mac. Accessed .
Where Castilion can help
- Investment advisoryWhat the data means for your own plans.
- Commercial and whole asset transactionsBuildings, floors and plots.
Weighing a decision this touches?
Our licensed team can talk it through with you, in confidence and without obligation.
Talk to an Advisor