Nakheel awards AED 1.4 billion for 176 more Palm Jebel Ali villas, due in 24 months
Nakheel awarded a main construction contract worth over AED 1.4 billion to Ginco General Contracting on 26 November 2026 for 128 beach villas and 48 coral villas on Fronds A to D of Palm Jebel Ali, with construction expected to take 24 months. It follows the AED 3.5 billion of villa contracts for 544 homes awarded in April 2026, so the island now has 720 villas under contract on its first six fronds.

Nakheel awarded a main construction contract worth over AED 1.4 billion to Ginco General Contracting for 176 villas on Palm Jebel Ali on 26 November 2026, The National and ARN News reported the same day. The homes sit on Fronds A to D and are expected to take 24 months to build, which takes the island to 720 villas under contract on its first six fronds since April 2026. For a buyer the award is the clearest evidence yet of a construction timetable on the fronds that were sold first, and the figure to hold against it is the fourth quarter 2028 completion target that Nakheel gave in April.
What Nakheel awarded on 26 November 2026
The contract covers 128 beach villas and 48 coral villas on Fronds A, B, C and D, per ARN News on 26 November 2026. The scope is civil, structural and architectural works, mechanical, electrical and plumbing installations, interior fit outs and external works, with construction expected to take 24 months from the start of works, the same report said. The National put the value at AED 1.4 billion, or USD 381 million, and said the villas are expected to be completed within two years.
Khalid Al Malik, chief executive of Dubai Holding Real Estate, Nakheel's parent, said "Palm Jebel Ali is a defining destination in Dubai's coastal growth", as quoted by The National. Gheyath Mohammad Gheyath, founder and chairman of Ginco General Contracting, said "This appointment extends our partnership with Nakheel on Palm Jebel Ali", as quoted by ARN News. Neither report gives villa sizes, bedroom counts or a handover date, and this article does not estimate them.
How it adds to the April contracts
The award builds on contracts worth over AED 3.5 billion for 544 villas that the Government of Dubai Media Office announced on 27 April 2026. Ginco General Contracting took 354 villas on Fronds A to D and United Engineering Construction took 190 villas on Fronds E and F, with construction scheduled to begin that quarter and completion targeted for the fourth quarter of 2028, per the release. The villas form part of a wider collection of ten architectural typologies, the Media Office said.
Taken together, Fronds A to D now carry 530 Ginco villas and Fronds E and F carry 190 UNEC villas, a total of 720 under contract. The November award follows Nakheel's unveiling of 44 beachfront villas from the Beach and Coral Collections on Frond F, per ARN News, and the release of 222 beachfront residences for sale in June 2026, per The National. Nakheel has not published sales figures for Palm Jebel Ali itself.
Where it sits on the island
Palm Jebel Ali has seven islands and 16 fronds with more than 120 kilometres of coastline and over 90 kilometres of beachfront, per ARN News on 26 November 2026. The National described the island as 13.4 kilometres long and twice the size of Palm Jumeirah when complete, planned for beachside homes for 35,000 families and 80 hotels and resorts. Those are plan figures, not delivered ones, as our Palm Jebel Ali community page notes.
The site already carries two Nakheel releases on the island. The Beach Collection on Frond J starts from AED 26.03 million on a 70/30 plan, with 20% on booking and 30% on completion estimated in March 2030, per developer material verified on 25 November 2026. Palm Central Private Residences on Frond D has estimated completion in October 2030 on 70/30 and 60/40 plans, per developer material verified on 23 November 2026. Frond D is among the four fronds in Ginco's contract, which is worth noting for anyone holding a Palm Central unit.
Inland, Nakheel's Palm Springs sold all 977 villas and townhouses in its first phase for AED 5.5 billion, per The National on 26 November 2026, as covered in our Palm Springs report. Jebel Ali Village began handing over 892 villas and townhouses in August 2026, the same report said.
What it means for investors
The useful reading is about sequence and evidence. Palm Jebel Ali was reclaimed in the early 2000s, paused for years and relaunched with a masterplan approved in 2023. Buyers who paid deposits on the first fronds were buying a plan. A main contractor with a 24 month programme on Fronds A to D, on top of a 544 villa programme targeted for the fourth quarter of 2028, is the point at which a frond becomes a building site with a date attached. The right question for an owner is which contractor holds their frond and when works commenced, because that start date is what the 24 month programme runs from.
For a buyer in the Americas the dirham is pegged at AED 3.6725 to the US dollar, so the AED 26.03 million entry price on Frond J is about USD 7.09 million and does not move with the exchange rate. Financing is the constraint. The Central Bank of the UAE caps a mortgage on an off plan purchase at 50% of value for any borrower under Circular 31/2013 as amended, and most lenders that accept off plan collateral release funds only at handover, so a buyer should plan to fund the 70% construction stage from cash. Our off plan mortgage page and non resident mortgage page set out how lenders treat foreign income at handover. US and Canadian owners who report foreign property at home should confirm the rules with an adviser; the reporting facts are on our US investors page.
Compare the frond villas with the mainland alternative before committing. Palm Springs sold 977 homes in one phase beside a metro station, per The National, and our Palm Springs versus Palm Jebel Ali piece sets the two against each other on price, plot and timing.
What to watch
Three dates matter. The first is the start of works under the Ginco contract, which fixes the 24 month clock. The second is the fourth quarter of 2028, Nakheel's stated target for the 544 villas awarded in April 2026. The third is any contract for the remaining fronds, for which neither announcement names a contractor. A fourth signal would be sales data for the island, which Nakheel has not released. Castilion Estates presents the Beach Collection on Frond J and Palm Central on Frond D, and our guide to how off plan purchases work in Dubai covers the escrow and registration steps that apply before any payment.
Questions and answers
How many Palm Jebel Ali villas are now under construction contract?
When will the new Palm Jebel Ali villas be finished?
Can a non resident get a mortgage on a Palm Jebel Ali villa?
What does the contract mean for someone who already bought on Palm Jebel Ali?
Sources
- Government of Dubai Media Office release on Nakheel's award of contracts worth over AED 3.5 billion for 544 villas on Palm Jebel Ali, 354 to Ginco General Contracting on Fronds A to D and 190 to United Engineering Construction on Fronds E and F, with completion targeted for the fourth quarter of 2028, 27 April 2026 (opens in a new tab). Government of Dubai Media Office. Accessed .
- The National report on the AED 1.4 billion (USD 381 million) contract to Ginco General Contracting for 176 villas, 128 beach and 48 coral, on Fronds A to D, completion within two years, the island's 13.4 kilometre length, 16 fronds, 35,000 families and 80 hotels, the 222 residences released in June 2026 and Palm Springs' AED 5.5 billion first phase, 26 November 2026 (opens in a new tab). The National. Accessed .
- ARN News (Dubai Eye 103.8) report on the main construction contract worth over AED 1.4 billion, the scope of civil, structural, architectural, mechanical, electrical, plumbing, fit out and external works, the 24 month construction period, the 120 kilometres of coastline and 90 kilometres of beachfront, and the earlier unveiling of 44 villas on Frond F, 26 November 2026 (opens in a new tab). ARN News. Accessed .
Where Castilion can help
- Off plan advisoryThe developer, the location and the contract, assessed first.
- New developmentsProjects Castilion is following.
Weighing a decision this touches?
Our licensed team can talk it through with you, in confidence and without obligation.
Talk to an Advisor